European Proceedings Logo

Industrialised Building System (IBS)/Off-Site Project Management Life Cycle

Table 1:

Construction Stage Best Practices for HCC
Briefing :Demonstrate the need Knowledge Management – Information sharing among project stakeholders for comprehensive Client Needs
Feasibility Study : isit worthdoing Trust/building confidence : To convinced project stakeholdersEvidence – QS prepared holistic costingKnowledge Management – Shared the advantages of HCC/IBS
ConceptualDesign 1:Consider the options Trust/building confidence – Main Contractors and HCC/IBS providers and Sub-consEvidence – Thorough QS Analysis on Costing and ViabilityManufacturability &Buildability- Practicality on site
ConceptualDesign 2:Choose the option Trust/building confidence- Transparency and ‘open book’ of advantages of HCC/IBS. Project Architect must ‘champion’ the promotion HCC/IBSEvidence – Visit the similar completed building/projectsKnowledge Management – Strategies the appropriate devices for project stakeholders to share the information. Proposed performance indicatorsManufacturability &Buildability – Establish interface registration as management tools of risk managementBuildability – Lead time project planning for cost and time management
Design 1:Work up chosen option Trust/building confidence : Client feedback being considered in Client Brief/Needs documentEvidence – Produce component samples, prototype and model of HCC/IBSKnowledge Management – Generate ‘Concrete Frame Profile’ (IBS Supply Chain Management), Manufacturability &Buildability – Improved repetition/mould user abilityBuildability –Realistic tolerances between IBS producers and project designers, Use Virtual Reality (VR) for managing the planning of projects
Design 2:Production information Knowledge Management – Agree on the communication strategy for On Site decision-makingManufacturability &Buildability- Take advice from precaster/IBS SuppliersBuildability – Optimised hook time for crane on site, Devised strategy to protect IBS providers, Set not to allow ‘unauthorised’ IBS providers to modified/ remedies IBS components
Construction 1: Off-site Manufacture Buildability – Carry out final Virtual Reality (VR) for Simulation manufacture, erection and complete construction process
Construction 2: On-site work Knowledge Management – As built building Survey to be shared for whole project stakeholders in HCC/IBS
< Back to article