Improvising Industrialised Building System Through the Adoption of Building Information Modeling

Table 1: Impact of fragmentation issue in IBS construction

Impact of fragmentation issue in IBS projects AI RII Rank
Lack of integration between constractors and designers 4.15 0.830 1
Lack of communication 3.66 0.732 5
Misconceptions and misunderstandings 3.47 0.694 8
Design clashes, omission and errors 3.99 0.798 2
Changes of design 3.99 0.798 2
Increase complexity of project 3.54 0.708 6
Rework 3.48 0.696 7
Increase cost of project 3.84 0.768 4
Time delays 3.20 0.640 9