The Project Environment Components In Project Activities In The Public Sector

Table 2:

Factors hampering the implementation of project management in the state authorities of the region Final score
1. Insufficient level of development of the regulatory framework and methodological support from federal authorities 4,3
2. Low activity, weak initiative and motivation of state authorities during the process of implementation of the project approach principles 3,1
3. Lack of necessary competences for project management (knowledge and skills) for civil servants 4,8
4. Weak level of technical and technological support of project activities 4,6
5. The conflict in the combination of functional and project approaches to management (double subordination) 4,2
6. The formal principle to the application of new approaches and methods of work (resistance to change) 2,5
7. Lack of interagency coordination of government bodies 4,5