S. No. |
EVA Enablers |
Mean |
Rank |
i. |
EVA contributes to achieving project schedule objectives. |
3.83 |
1 |
ii. |
EVA provides early warning of performance problems. |
3.78 |
2 |
iii. |
EVA allows objective communication among project stakeholders |
3.53 |
3 |
iv. |
EVA contributes to achieving project cost objectives. |
3.47 |
4 |
v. |
EVA is a cost-effective tool for performance management. |
3.37 |
5 |
vi. |
EVA contributes to improving project scope definition and prevents scope creep. |
3.02 |
6 |
|
Kendall’s coefficient of concordance (w) |
0.050 |
|
Level of Significance |
0.000 |